Coordination meetings often start with a number: several hundred clashes, down from last week. The number is easy to report and hard to act on. A clash count mixes real conflicts with duplicates, tolerance artefacts and issues that were resolved but never re-checked. What a project actually needs is a manageable set of issues with an owner, a decision and a record of closure. This article describes that lifecycle.
Why clash counts mislead
A raw clash result is a geometric observation, not an issue. The same pipe passing through the same beam can appear in several tests, at several tolerances, across several viewpoints. Changing a tolerance can halve the count without changing the building.
- Duplicates: the same conflict detected by more than one rule or viewpoint.
- False positives: elements that are allowed to intersect, such as sleeves or embedded items.
- Stale results: clashes from a model revision that has already been updated.
- Unactionable volume: a list too long to review, so the important items are lost.
None of this means clash detection is unreliable. It means the output needs grouping and judgement before it becomes a coordination issue.
The issue lifecycle
A coordination issue moves through six stages. Skipping one is usually why an issue reappears later.
1. Detect
Run the agreed tests against the current model revisions, at the agreed tolerances. Record which models and revisions were used, so the result can be reproduced.
2. Group
Combine duplicates and related clashes into one practical issue: a service crossing a structure at one location is one issue, not eight. Grouping by location and system makes the list reviewable.
3. Assign
Give each issue an owner and the discipline responsible for the decision. Ownership is usually agreed before the cycle starts, not negotiated during the meeting.
4. Resolve
Resolution can be a design change, a modelling change, or an accepted condition with a recorded reason. The decision belongs to the responsible designer, not to the coordination team.
5. Re-check
Re-run the same test on the updated revision and confirm the issue is closed. A re-check against a different viewpoint or tolerance proves nothing.
6. Close
Record the resolution, the revision that contains it and the date. A closed issue without that record tends to reopen.
What a useful issue log contains
The log is the coordination record. It should be readable without the meeting that produced it.
- A stable issue ID that is never reused.
- Location, level and grid reference.
- Disciplines and systems involved.
- A short description of the conflict, not a clash-test name.
- Status, owner and the date raised.
- The target resolution point and, later, the actual resolution.
- The linked viewpoint and the model revisions checked.
- The closure note and the revision that resolves it.
Before the first cycle: what to agree
Most coordination disputes trace back to something that was never agreed. A short protocol at the start prevents arguments about whose clash counts.
- Tolerances per discipline pair, and the tests that will be run.
- Which model formats and revisions are exchanged, and by when.
- An ownership matrix: who decides, who updates, who is informed.
- Status definitions, so open, in progress, resolved and closed mean the same to everyone.
- Closure criteria: what evidence counts as a re-check.
- The review cadence and who attends.
The protocol does not need to be long. It needs to be specific enough that a disagreement can be settled by reading it.
Running a coordination cycle
A cycle is a repeatable sequence, not a single meeting.
- Confirm the model revisions and that each contributor has issued the agreed content.
- Federate the models and check alignment and coordinates.
- Run the agreed tests and group the results.
- Review the grouped issues with the disciplines and confirm ownership.
- Update models or record accepted conditions.
- Re-check the same tests on the new revisions.
- Issue the updated log and report, carrying open items forward.
The cadence is a project decision. What matters is that each cycle closes more issues than it opens and that the log remains the single record.
Reporting that leads to decisions
A report that lists every clash is a data dump. A report that supports a meeting organises issues by the decision they need.
- Open issues by owner and discipline, not by clash test.
- Age and target date, so overdue items are visible.
- Items closed since the last cycle, with the revision that resolved them.
- Accepted conditions, recorded with the reason they were accepted.
- A short summary of what changed in the models since the previous report.
The report should be readable in a few minutes. Detail belongs in the log, not in the summary.
Roles and decisions
Coordination works when three responsibilities stay separate.
- Design responsibility: the designer decides whether to move the structure, the service or both.
- Coordination responsibility: collecting models, running tests, grouping issues and tracking status.
- Production responsibility: updating models or drawings where that is in scope.
A production team can federate, report and re-check. It should not decide a design resolution, and a contractor should not close an issue that a designer has not accepted.
Common failure modes
- Models are federated before every contributor has issued the same revision.
- Issues are assigned to a company rather than a person or role.
- An issue is closed because it disappeared from a later test, not because it was resolved.
- Tolerance arguments replace resolution decisions.
- The report grows but the open-issue list does not shrink.
- Issue IDs change between cycles, breaking the audit trail.
Each of these is a process problem rather than a modelling problem, which is why it is worth fixing before adding more tests.
An illustrative cycle
A contractor receives architectural, structural and MEP models for a coordination cycle. The models are federated and checked for alignment; two contributors have issued an older revision, so the cycle starts with a revision request rather than a clash review. Once aligned, the tests produce a long raw list, which is grouped into a smaller set of location-based issues. Owners are confirmed in the review meeting, updates are issued, and the same tests are re-run on the new revisions. Most issues close; the remainder carry a recorded reason and a target date. The value of the cycle is not the reduction in the raw count, but the smaller list of issues that are actually resolved. This is an illustrative cycle, not a description of a specific BuildLayer Studio project.
Conclusion
Coordination is issue management with geometry attached. Detect and group carefully, assign clearly, resolve with the responsible designer, re-check on the same basis, and close with a record. Done consistently, the clash count becomes a by-product rather than the objective. For the production side, see BIM coordination; model inputs are covered in BIM modeling, and revision discipline in Standardisation for Consistent Outputs.